Emerson’s Expertise and Technology Helps Qatargas Save Energy and Reduce Greenhouse Gases

艾默生过程管理公司为卡塔尔天然气项目,将1.6万吨,每年减少温室气体排放提供自动化和工程服务。

This content was submitted directly to this website by the supplier.

艾默生过程管理公司为卡塔尔天然气项目,将1.6万吨,每年减少温室气体排放提供自动化和工程服务。

Now fully operational, the Jetty Boil-Off Gas (JBOG) Recovery facility is the biggest of its kind and one of the largest environmental investments in the world. It is expected to recover more than 600,000 tonnes of liquefied natural gas per year – equivalent to the energy supply for more than 300,000 homes.

The facility is designed to recover the gas flared during liquefied natural gas (LNG) loading at the six LNG berths in Ras Laffan Port. The gas is compressed and sent to the Qatargas and RasGas LNG production facilities for use as fuel or as LNG.

Emerson won this multi-million dollar contract based on its leadership in oil and gas automation technologies, services, and expertise. Emerson specialists managed key elements of the project including automation engineering, configuration, startup, training, commissioning support and other services.

“Without Emerson’s highly skilled team, completing the project would have been vastly harder,” said Michael Koo, Qatargas’ Project Manager.

Emerson’s automation solution for the project included the DeltaV™ distributed control system to control and monitor operations, as well as the company’s Fisher® control valves and Rosemount® measurement instruments.

“艾默生团队欢迎这一机会,帮助卡塔尔天然气公司安全地执行该项目,可靠,高效地,”艾默生为卡塔尔天然气公司高级项目经理Alvinne雷克斯Abaricia说。“我们能够采取灵活的方法来提高效率,比如在并行测试的硬件和软件,以及数十位专家带来了我们自己的组织,以及其他供应商来管理现有的和新的系统之间的接口。”

The $1 billion JBOG project is a landmark for the State of Qatar, demonstrating its commitment to balance industrial expansion with care for the environment.

>>For more information, click这里.